The Department of Rural Roads has ordered a seven-day closure of the Suan Liap Interchange Bridge on Ratchaphruek Road to urgently inspect cracks found on the piers. The damage is suspected to be linked to the 2025 earthquake. Plans are underway for a joint site inspection with the Council of Engineers to re-examine the structure.
Following the discovery of cracks and separations between the bridge and its piers on the outbound Suan Liap Interchange Bridge on Ratchaphruek Road, authorities closed the bridge heading towards Taling Chan to conduct inspections starting yesterday evening (25 Nov). This closure has caused extended traffic congestion, as previously reported.
In the latest update, Mr. Phichit Hunsiri, Director General of the Department of Rural Roads, revealed that cracks were found on the piers beneath the Suan Liap Interchange Bridge on Ratchaphruek Road. Officials detected abnormalities while investigating theft of electrical cables, prompting an immediate closure of the bridge to ensure public safety. He acknowledged public criticism and apologized for the inconvenience caused by the closure.
Regarding the cause of the cracks, it is suspected they relate to the 2025 earthquake. Separation was observed between concrete blocks of the bridge, but internal steel reinforcement remains securing the main structure. A thorough inspection of the reinforcement and internal structure is required. If the steel is still strong, repairs will focus on the damaged areas and are expected to take about three to four days. However, if structural steel damage is found, the repair timeline will need to be reassessed.
The Department of Rural Roads has ordered the bridge closure for seven days to ensure safety. Detour signs will be installed today to guide motorists and prevent confusion. Tomorrow, the Council of Engineers will also join the inspection to verify the bridge’s structural safety before it reopens.